Estimates

π mal Daumen = ?

What is the accuracy of the estimate?

For cost estimates, always specify two numbers: minimum and maximum. As project planning progresses, the uncertainties become ever smaller. For example according to PMI:

Project Progress Boundary Values
ROM – Rough Order of Magnitude Estimate -50% … +100%
Preliminary Estimate -25% …   +50%
Budget Estimate -10% …   +25%
Definitive Estimate   -5% …   +10%
Final Estimate 0%

Results from previous projects are an important input. The maturity of the organization influences the accuracy of the estimates.

Three-point estimation from PERT

  • Estimate = (Optimistic + 4 * Realistic + Pessimistic) / 6
  • Standard Deviation = (Pessimistic - Optimistic) / 6
  • Uncertainty = root of the sum of the squares of all standard deviations

Function Points

Agile Projekte

  • story points, relative to each other
  • estimated exams
  • planning poker

Additional